107. Parallel Courses — Minimum Semesters

CoreFreeze each ready batch to model unlimited parallel unit-duration semesters

Take any number of currently eligible courses in parallel during a semester. A course becomes eligible only after its prerequisites have been completed in earlier semesters.

Courses finishing in the same semester cannot unlock a dependent for that same semester. Prerequisite cycles make a complete schedule impossible.

Example 1

Input

n=5, relations=[[0,2],[1,2],[2,3]]

Output

3

Explanation: Semester 1 takes 0,1,4; semester 2 takes 2; semester 3 takes 3. Independent work does not add semesters.

Example 2

Input

n=3, relations=[[0,1],[0,1],[1,2]]

Output

3

Explanation: Both 0→1 occurrences discharge together; 1 still waits until the next semester.

Example 3

Input

n=3, relations=[[0,1],[1,0]]

Output

-1

Explanation: Course 2 can finish, but the remaining cycle prevents a full schedule.

Constraints

  • 0 <= n <= 105
  • 0 <= edge occurrences <= 2 * 105
  • 0 <= vertex label < n
Hints
Hint 1

Unlimited parallel work suggests complete readiness batches.

Hint 2

Use incoming counts, but freeze the queue length before each semester.

Hint 3

Compare the last batch number with longest prerequisite-chain length and verify full completion.

Practice on LeetCode ↗ · Premium
Code
Saved on this deviceLn 1, Col 1

Independent courses share the first semester

5
[[0,2],[1,2],[2,3]]
3